Builders in Breukelen

Building work and maintenance in Breukelen, at a fixed price for the work as described and paid in four instalments.

Breukelen lies in the municipality of Stichtse Vecht and is built around the old ribbon development along the Vecht. The Herenstraat, the Brugstraat and the Kerkbrink form the historic centre, with the country estates around it, of which Nijenrode is the best known. Part of that centre is a protected village area (beschermd dorpsgezicht), which sharply limits what can be done on the street side.

In practice that means the following. The view from the public road is fixed: window layout, roof shape, colour scheme and the profile of the pointing. Adding space therefore happens at the back or upwards, and whatever happens there has to stay invisible from the street. A dormer at the rear is usually possible; a full depth loft conversion, almost never.

The houses on the water between the Brugstraat and the Zandpad are partly deep and narrow, with foundations from different periods: a front house on strip footings and a rear addition from the 1930s or 1950s on something else. For an extension or a structural opening that is the first question to answer, because two parts of a building that settle differently open a crack along the joint that no amount of plastering will fix.

In the newer parts towards the Broekdijk and Breukelen-Noord none of that applies and it is the standard work: an extension at the back, an opening through to the kitchen, and replacing window frames and pointing from the original building period.

Street scene and building style in Breukelen. Generated image, not a job that was carried out.

What decides things here

  • Protected village area around the Herenstraat, the Brugstraat and the Kerkbrink
  • Deep, narrow plots along the Vecht with building parts from different periods
  • Additions are only possible at the rear and must stay invisible from the street
  • Permits run through the municipality of Stichtse Vecht

How building work in Breukelen runs

Nine steps. Each one states who is there, how long it takes and what you pay at that moment. On the steps where money actually changes hands, the amount is set in the heading face under "What you pay" and the step number is filled in. Handover is called oplevering in Dutch, and it is the step your contract will refer to.

  1. Step 1: Phone call

    You call, or leave a callback request. We ask about the type of work, the year the house was built, the place and roughly what you have in mind. By the end of that call you know whether this is work we take on and whether your budget and your plan meet. If they do not, we say so there and then.

    Who is there
    You and the work planner
    How long
    15 minutes, within one working day
    What you pay
    Nothing
  2. Step 2: Survey at your house

    We come round, measure up, look in the crawl space (kruipruimte) and the loft, and assess the foundation, the structure and the connections to the existing house. For a loft conversion or a structural opening we establish whether a structural engineer (constructeur) is needed. You hear on the spot which price range is realistic.

    Who is there
    You and the site manager
    How long
    45 to 90 minutes, within two weeks
    What you pay
    Nothing
  3. Step 3: Quotation with a fixed price

    You receive a quotation (offerte) with a fixed price for the work as described, a list of what is explicitly not included, and provisional sums (stelposten) for items you choose yourself. No figure in it is an estimate: what the quotation says stands, as long as the work does not change.

    Who is there
    We supply it, you read it
    How long
    Within five working days of the survey
    What you pay
    Nothing
  4. Step 4: Design, calculation and permit

    Only where the work requires it. Drawings, a structural calculation, and the permit application (omgevingsvergunning, the Dutch building permit) with the municipality of Stichtse Vecht or De Ronde Venen. If the permit is refused, the project stops and you pay for this phase only, at an amount stated on the quotation in advance.

    Who is there
    Draughtsman, structural engineer and the municipality
    How long
    4 to 12 weeks, depending on the procedure
    What you pay
    The cost of this phase, named separately on the quotation
  5. Step 5: Planning and start date

    The start date is fixed in writing, with a week by week plan and the days on which it will be loud or dusty. Materials with long lead times are ordered in this phase, so the job does not come to a halt halfway through waiting for a window frame.

    Who is there
    You and the work planner
    How long
    1 to 2 weeks
    What you pay
    Nothing
  6. Step 6: Work starts on site

    Day one: fencing, floor protection, a place to unload, and demolition. From this day there is one site manager who is your point of contact and whom you can call directly on working days.

    Who is there
    The site manager and the crew
    How long
    Day 1
    What you pay
    First instalment: 30 per cent
  7. Step 7: Shell complete

    Foundation, structure, brickwork, roof and window frames are in place and the work is wind and watertight. This is the moment you can stand in the new space for the first time, and the last moment changes are possible without demolition.

    Who is there
    The site manager walks it through with you
    How long
    Depends on the job, usually after 3 to 6 weeks
    What you pay
    Second instalment: 30 per cent
  8. Step 8: Services and fit-out

    Electrics, water, heating and ventilation are installed and tested. Then plastering, floors, tiling and painting. This phase is quiet but long; it is the phase in which people get impatient and in which the weekly plan matters most.

    Who is there
    Installer, plasterer and fit-out crew
    How long
    2 to 5 weeks
    What you pay
    Third instalment: 30 per cent
  9. Step 9: Handover and snagging list

    We walk the work through together and write down everything you see, however small. In Dutch this step is the oplevering and the list is the opleverlijst. That list is cleared within fifteen working days. Only once every point on it is signed off does the last instalment fall due.

    Who is there
    You and the site manager
    How long
    1 to 2 hours, points cleared within 15 working days
    What you pay
    Final instalment: 10 per cent, after the snagging list is cleared

The payment schedule

Nothing is paid in advance before work starts.

Each block in the bar is as wide as its share of the contract sum (aanneemsom). The pale block on the right is the final 10 per cent: it only falls due after handover (oplevering), once every point on the snagging list has been dealt with.

Payment schedule in four instalments, with the share of the contract sum and the moment of payment
InstalmentShareWhen
First instalment30%The day work starts on site
Second instalment30%Shell complete, the work is wind and watertight
Third instalment30%Services tested and fit-out complete
Final instalment10%After handover, once every snagging point is cleared
Together100%

The cost of drawings, the structural calculation and the permit sits outside these four instalments and is named separately on the quotation, so you can see what you would be out of pocket if a permit is unexpectedly refused. The total being paid in instalments is the contract sum, called the aanneemsom in your contract.

Questions about building work in Breukelen

Can I have a loft conversion in the centre of Breukelen?

Inside the protected area, almost never across the full depth, because the ridge height and the view from the street both change. A dormer at the rear is usually open to discussion. We check it with the municipality in advance and put the answer in writing before there is a price.

My front house and rear addition are settling differently. What now?

Measure first, repair second. We fit measuring points and follow them for several months. If the movement has stopped, cosmetic repair will hold. If it is still moving, foundation repair is the answer and filling cracks is pointless.

Are there separate rules for pointing in the centre?

Yes. Inside the protected area, pointing has to come back in the same colour, composition and profile, and old brickwork does not tolerate a hard cement mortar. We work there with a lime-based mortar and lay a sample panel before doing a whole elevation.

Talk through your plan in Breukelen

Calling is quickest. In fifteen minutes you know whether this is work we take on and whether your plan and your budget meet.

Other places in our area

Ask us to call you back

Six questions. With these answers we can tell you in the first call whether your plan fits your budget, instead of finding that out after a visit.

The year the house was built, roughly what you have in mind, whether a drawing already exists.

Your details are used only to contact you about this request. How long we keep them is set out in the privacy statement, linked at the bottom of every page.

Call usCall me back